| Cover Story |
| Columns |
| Construction Law: Riskier Business |
| Executive Advice | |
| By Kevin Hudson and Matthew Spivey | |
| Tuesday, 18 March 2008 | |
![]() Beginning with the 1987 set of construction documents, which were generally viewed as acceptable to most contractors, the American Institute of Architects (AIA) began a process of revising its construction documents every 10 years. Each revision has yielded more provisions that were unacceptable to contractors, and the 2007 set is no exception. As part one of a two-part series, we will evaluate the 2007 AIA documents from the contractor’s perspective. Concerns are divided into two main areas. Part one examines the responsibility shift in the 2007 documents from risk previously placed on the architect to risk that is now placed on the contractor. Part two will examine defects and pitfalls in the claims process, and the likely result that contractors will lose valid claims, including claims for concealed conditions, based on a failure to follow procedure. AIA will allow the use of the 1997 version of the documents until May 2009, even though the 2007 documents are now available. It is important to have an understanding of the changes now because owners were entitled to begin using the 2007 documents as of January. This allocation of risk was further supported by the well-known Spearin doctrine. This is the proposition that when an owner’s contract prescribes specific design performance requirements, it carries with it the implied warranty that if the plans and specifications are followed, the construction will be adequate and the contractor does not bear the liability if it is not. (See United States vs. Spearin, 248 U.S. 132 (1918). Coordination and Design Issues A201-1997 section 3.2.1 details various requirements related to a contractor’s obligation to review contract documents and site conditions, and to report any “errors, inconsistencies or omissions discovered by contractor … to the architect as a request for information.” The stated purpose is to facilitate “construction by the contractor.” Under Section 3.2.3 of the 1997 version, a contractor was not responsible for a design error unless the contractor “recognized such error, inconsistency, omission or difference and knowingly failed to report it to the architect.” A201-2007 Section 3.2.2 revises Sections 3.2.1 and 3.2.3 significantly. First, the stated purpose is changed to “coordination and construction by the contractor,” which is a design concept and ordinarily the responsibility of the architect. Next, Section 3.2.2 imposes a “negligence standard on the contractor for failing to report any error, inconsistency or omission.” Under the 2007 documents, the question will now become whether the contractor should have known that the design documents were insufficient for the task. In the Big Dig example, the 2007 documents would have supported the exact contentions that were advanced, making the contractor’s efforts to hold the architect responsible for design errors much more difficult. Instead of the issue being whether the contractor actually knew that the design documents would not support the work, the question will become whether a sophisticated contractor, who has built tunnels for years, should have known that the design documents were insufficient. The 2007 documents, however, take one more step to exculpate the architect and impose liability on the contractor. A201-1997 Section 4.2.2 included an obligation on the architect “to endeavor to guard the owner against defects and deficiencies in the work.” The purpose of this provision was to facilitate involvement by the architect during construction in ensuring that the design would produce non-defective work. Even if the architect was negligent in the design, he or she was given an opportunity to evaluate the work during construction and stop the work as necessary to correct the negligence. For example, if a light tower was designed inadequately, such that it was incapable of carrying a load, an architect would have the opportunity during the construction to observe the light tower and the fact that it was out of plumb, and then take corrective action. A201-2007 Section 4.2.3 removes the obligation to guard against defects and deficiencies, and makes the architect responsible only to report “known deviations” from the contract documents. The 2007 documents are precisely the opposite of a correct allocation of risk. Instead of the architect being responsible to coordinate work during actual construction and confirm during that process that his or her work was sufficient and accurate, the risk of defects and deficiencies from the architect’s work during the construction now appears to be shifted to the contractor. Incredibly, the architect now receives the protection afforded by “actual knowledge,” while the contractor is charged under penalty of negligence with evaluating the design of another. The practical implications are such that either the contractor will take on this responsibility with such zeal that constant and unnecessary communications pointing out possible errors and inconsistencies will ensue, or the contractor will instead risk being measured on a negligence standard by the owner if the project progresses with delay or other problems caused by design specifications. Further, the revisions, as well as recent case law, seem to imply a higher hurdle for the contractor who seeks compensation for delays or changes in work related to defective design in the plans and specifications. |
|
| < Previous Story | Next Story > |
|---|