| Cover Story |
| Columns |
| Commercial |
| Executive Advice |
| Heavy Highway |
| Material/Equipment |
| Residential |
| Schools/Healthcare |
| Specialty Trades |
| Sustainablilty |
| CH2M Hill – Brightwater Wastewater Treatment Plant |
| Featured Content | |
| By Kate Burrows | |
| Tuesday, 28 October 2008 | |
![]() Tradesmen finish the last of the digester slab foundation pours at the Brightwater Wastewater Treatment System. CH2M?Hill provided the engineering and architectural design services for the treatment plant. The story behind the need for new infrastructure in King County, Wash., is the same as anywhere else, but the magnitude of a new $1.8 billion wastewater treatment system here is anything but typical. Population growth – paired with aging treatment facilities – has spurred the need for a cutting-edge wastewater treatment system that can serve the needs of communities in King and Snohomish counties. Labeled the Brightwater Treatment System, the project will serve the fast-growing northern portion of King County’s wastewater service area. The project consists of a treatment plant with capacity to treat up to 36 million gallons of wastewater per day, an off-site influent pump station, reclaimed water distribution facilities and conveyance tunnels. A new 13-mile pipeline will convey the treated effluent to a mile-long outfall where it will be released into Puget Sound. The $437 million regional wastewater treatment facility will be the third plant to serve the greater Seattle area. The total project cost for the Brightwater system is $1.8 billion. King County’s wastewater treatment utility protects public health and water quality for 17 cities, 17 local sewer districts and more than 1.4 million residents in King, Snohomish and Pierce counties. CH2M Hill is providing engineering and architectural services for the treatment plant. According to Project Manager Pat Burke, prior to being selected for the Brightwater treatment plant design, CH2M Hill completed facility siting studies and assisted with preparation of an environmental impact statement for the wastewater system. The offsite conveyance facilities were designed and are being constructed by other companies. CH2M Hill teamed with Brown and Caldwell and several other key sub-consultants to pursue the Brightwater design, and was later joined by Seattle-based Mithun Architects + Designers + Planners. “Our combined resources provided the county with the industry-leading technical expertise and depth of design talent required to select the right treatment technologies, appropriate mitigation measures and then deliver the project,” says Burke, who joined the firm six years ago to work on Brightwater. According to Burke, the need for a new north end treatment plant – now known as Brightwater – was identified in t he County’s Regional Wastewater Services Plan, adopted in 1999. CH2M HILL became involved is siting studies shortly thereafter. Valued at approximately $47 million for the company, “the Brightwater treatment plant involves some 6,000 drawings, and during peak periods we had over 150 staff engaged in producing the design,” Burke explains. “With our combined resources, we were able to meet all schedule milestones for design deliverables. “At the peak of production, we had over 20 sub-consultants participating in the project, including minority and women-owned businesses and key advisors on issues such as LEED, seismic issues and landscape design.” The treatment plant will be constructed under two separate contracts with King County. Hoffman Construction Co. is acting as a general contractor/construction manager. Hoffman is responsible for the overall site/civil construction, as well as the liquids processing facilities. Kiewit is constructing the solids and odor control facilities under a traditional design/bid/build contract. Freshwater testing and start-up is scheduled for late 2010 with commissioning in early 2011. Lessening the environmental impact of the overall project was a priority. Prior to construction, the project team conducted a four-year technical analysis and public participation process to select the most suitable locations for the various facilities based on engineering, community and environmental reasons. Brightwater includes constructed wetlands and wildlife habitat that mitigate project impacts. Open space at the North Mitigation Area has been enhanced by reconstructing degraded streams that had been routed into culverts. Paving has been minimized, reducing the runoff potential from the site. Storm water management includes detention, sedimentation and polishing through constructed wetlands. These enhancements will improve water quality in nearby Little Bear Creek, Burke states. The treatment plant itself uses technology to reduce its footprint on the environment. “The split-flow membrane bioreactor [MBR] process, combined with chemically-enhanced primary treatment, reduces the overall footprint of the treatment plant compared to other, more conventional alternatives,” Burke explains. The unique split-flow MBR process works in tandem with chemically enhanced primary clarification. “The split-flow process configuration allowed MBR technology to be applied to Brightwater at a cost competitive with conventional activated sludge,” Burke notes. “Brightwater will produce up to 21 million gallons per day of reclaimed water from the MBR process.” Also, by using the general contractor/ construction manager delivery, Hoffman Construction has been onboard since pre-design, providing invaluable review and input, Burke says. “The project has benefitted from the County’s collaborative approach to construction,” he adds. “We have regularly scheduled work sessions with the construction management team, Hoffman, Kiewit and their key subs where we jointly focus on construction issues, contractor value-engineering ideas, change orders and the like. “As we get a bit further along, we’ll begin similar meetings focused on testing and start-up, again in a highly collaborative environment.” Collaboration between the owner and CH2M Hill has obviously been integral to the project’s success. “The continuous engagement of the owner’s operations and maintenance staff – people who have been with us from the earliest days of process selection right through development of detailed wiring diagrams – has been a tremendous asset,” Burke notes. Today, the 100 percent employee-owned firm remains a leading wastewater treatment firm, but also specializes in critical infrastructure and related systems, government, industrial, energy and environment-related projects. Headquartered in Englewood, Colo., the company’s northwest operations are heavily involved in wastewater infrastructure and other large civil works projects. “Needless to say, it’s becoming very competitive,” Haight says about the Northwest. Yet, the region appears to be less impacted by the national recession than are other parts of the country. “There is a lot of new industry out here that are not feeling as much of the recession. Financing and manufacturing are not the core businesses out here. The technology and energy sectors are industries bucking national trends.” The company’s construction arm has felt the increase in steel and concrete, for example, just as other businesses have. “The biggest thing is that projects are costing our clients more,” Haight says. “Part of what we do as problem-solvers is do more with less.” |
|
| < Previous Story | Next Story > |
|---|